X

Project Goal: A new pond is being constructed at the southeast corner of the Zuni Road and Pennsylvania Street intersection to address peak capacity issues within the Dallas Storm Drain System. The new pond will have an approximate depth of 14 feet and have a volume of approximately 15 acre-feet. Storm drain connections and improvements will occur within both adjacent roadways. The pond, scheduled to be completed in May 2026, will be fenced and gated.

Construction Update: Excavation for the pond began in December 2025 and is now complete. Compass is in the process of building the concrete toe wall to reinforce the slopes. The CMU (concrete masonry unit) wall on the south side of the site is completed. Concrete footings are being poured for the decorative walls along the west, east, and north sides of the project.

Aerial photograph of construction at the Zuni-Penn pond, facing

Aerial photograph of the project site in February 2026

[Updated 02/25/2026]